Litchfield Advances $23 Million Sewer Overhaul and Approves $112,000 in Emergency Water Plant Repairs

Litchfield City Council Meeting | April 2, 2026

Article Summary: The Litchfield City Council moved forward with massive infrastructure planning for its water and wastewater facilities while approving emergency expenditures to address catastrophic failures at the water treatment plant.

Litchfield Infrastructure Key Points:

  • Approved $112,699.03 in emergency repairs for the water plant, including a new PAC silo and security system, waiving competitive bidding.

  • CMT Engineering outlined a $22 to $23 million rehabilitation of the aging wastewater treatment plant, targeting state loans and principal forgiveness.

  • Water clarifiers have been cleaned and filters rebuilt, leading to immediate and noticeable water quality improvements.

  • New 8-inch water lines and a water tower cleaning are underway to address ongoing distribution and quality issues.

The Litchfield City Council on Thursday, April 2, 2026, tackled a series of critical infrastructure hurdles, unanimously approving emergency expenditures for the city’s water treatment plant while previewing a massive $23 million overhaul of the wastewater facility.

The emergency water plant repairs come after what the city’s administration described in agenda documents as a “catastrophic failure of its chemical feed system.” After site visits from both CMT Engineering and HMG Engineering, a voluminous list of immediate corrections was identified.

Alderman Bob Garcia motioned to waive customary bidding procedures to authorize $112,699.03 in emergency fixes. The expenditures include $83,343.00 for a Powered Activated Carbon (PAC) Silo, $4,446.20 for Chlorination and Ammonia Emergency Close Systems, and $24,909.83 for a comprehensive water plant security and access control system to be installed by Heart Technologies.

Christie from CMT Engineering provided an encouraging update on the water plant’s ongoing recovery. A Request for Proposals (RFP) for contract operations is currently out, with vendors touring the facility. Meanwhile, critical deferred maintenance is finally being addressed. Both clarifiers have been completely cleaned out, and the rehabilitation of three filters—comprised of sand and granular activated carbon—is underway.

The results are already visible. “The water after the clarifiers actually had a turbidity that was below the finished water level,” Christie told the council, noting the dramatic reduction of particles in the water. She added that the plant staff’s morale has skyrocketed as they receive proper training on troubleshooting and system functions. “The sense of pride in ownership that’s going on out there is just leaps and bounds from where it was.”

On the distribution side, the city is advancing a $1.5 million water project on the west side of the railroad tracks, funded by a grant, alongside a $2.2 million project to reroute an 8-inch water line on the east side of the lake. A comprehensive cleaning of the water tower is also imminent, which officials hope will further decrease resident complaints regarding water quality.

Simultaneously, the city is racing against the clock to secure funding for a massive overhaul of its wastewater treatment plant, which has reached the end of its extended life. The $22 to $23 million project will heavily focus on replacing deteriorating mechanical components while preserving the structurally sound concrete basins to save costs.

“At a wastewater plant, everything is concrete because the wastewater is corrosive. The structures have like a 50-to-100-year life expectancy. It’s the mechanical components that have that 20-year life expectancy,” Christie explained to the council. “The most economical infrastructure that you have is what you’ve already used and paid for.”

To fund the wastewater overhaul, Litchfield is preparing an application for the State Revolving Fund (SRF) loan program. The city is aggressively pushing to finalize designs and secure necessary construction permits to be placed on the state’s “intended use” list by July 1. Achieving this status is highly competitive but critical, as it opens the door to “principal forgiveness”—the EPA equivalent of grant money based on the city’s median household income.

“We don’t want to lose that principal forgiveness,” Christie emphasized, warning that missing the fiscal cycle could force the city to compete against a different pool of projects the following year with no guarantee of the same financial assistance.

The council will consider an engineering design contract at its next meeting to ensure the project meets the strict state deadlines.

Leave a Comment





Latest News Stories

Signature process begins to ban large data centers in Ohio

Signature process begins to ban large data centers in Ohio

By David BeasleyThe Center Square Sponsors of a proposed constitutional amendment that would ban the construction of any new large data centers in Ohio have cleared another hurdle in getting...
U.S. Supreme Court agrees to hear veteran's benefits challenge

U.S. Supreme Court agrees to hear veteran’s benefits challenge

By Andrew RiceThe Center Square The U.S. Supreme Court agreed on Monday to hear an Army veteran's challenge over reduced disability benefits. The court agreed to hear Johnson v. United...
Supreme Court declines to hear challenge to Illinois public transport gun ban

Supreme Court declines to hear challenge to Illinois public transport gun ban

By Andrew RiceThe Center Square The U.S. Supreme Court on Monday declined to decide whether individuals can carry firearms on public transportation. The court declined to take up Schoenthal v....
Illinois Quick Hits: Report says Pekin Bowling Center 'taxed out of business'

Illinois Quick Hits: Report says Pekin Bowling Center ‘taxed out of business’

By Jim Talamonti | The Center SquareThe Center Square Sunset Lanes in Pekin is set to close later this month as the bowling center’s owner says it is being “taxed...
Tiffany vows to end subsidies for data centers in Wisconsin

Tiffany vows to end subsidies for data centers in Wisconsin

By Jon StyfThe Center Square Wisconsin congressman and candidate for governor Tom Tiffany said that he will “end subsidies for data centers in Wisconsin” if he becomes governor. Tiffany was...
montgomery county Graphic Logo.4

Roads & Bridges Committee Approves Over $120,000 for Local Bridge Infrastructure

Montgomery County Roads and Bridges Committee | March 2026 Article Summary: The Montgomery County Roads and Bridges Committee advanced two major infrastructure repair projects and formalized a road use agreement...
Litchfield School Logo Graphic.5

Litchfield Approves 2026-2027 Student Fees, Mandates Shot Clock Workers in New Officials Pay Scale

Litchfield Community Unit School District #12 Board of Education Meeting | March 19, 2026 Article Summary: Preparing for the upcoming academic and athletic seasons, the Litchfield School Board authorized the...
Firefighter age bill stalled despite union backing

Firefighter age bill stalled despite union backing

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – A proposed Illinois bill aimed at addressing firefighter shortages by lowering the minimum hiring age has...
Litchfield Panthers Softball Graphic

Williamsville’s Explosive Offense Overwhelms Litchfield in 16-0 Tournament Shutout

The Williamsville varsity softball team brought a relentless offensive attack to Saturday's tournament matchup, overpowering host Litchfield for a decisive 16-0 run-rule victory in four innings. Williamsville wasted no time...
Montgomery County Finance Committee

Finance and Budget Committee Reaps $11,444 Premium Refund, Shifts Administrative Expenses

Montgomery County Finance and Budget Committee | March 2026 Article Summary: The Montgomery County Finance and Budget Committee processed a nearly $11,500 workers' compensation premium refund and approved shifting universal...
Litchfield Panthers Softball Graphic

Rochester’s Early Offensive Surge Overwhelms Litchfield in 10-0 Shutout

A ten-run barrage across the first two innings propelled the Rochester varsity softball team to a commanding 10-0 neutral-site victory over Litchfield on Saturday. Taking immediate control of the non-conference...
Lawmaker criticizes surplus spending bill

Lawmaker criticizes surplus spending bill

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A proposal aimed at helping local governments manage retiree health care costs is drawing differing views...
Litchfield Panthers Softball Graphic

Clark’s Homer and Lurkins’ Shutout Power Greenville Softball Past Litchfield 15-0

The Greenville varsity softball team showcased dominance on both sides of the diamond Friday, cruising to a 15-0 home victory over Litchfield. Fueled by an explosive offense and a lockdown...
solar panels photovoltaics in solar farm

Development Committee Advances Wind and Solar Ordinance Updates Amid Public Scrutiny

Montgomery County Development and Personnel Committee | March 2026 Article Summary: The Montgomery County Development and Personnel Committee recommended sweeping changes to the county’s wind and solar zoning ordinances to...
Litchfield School Logo Graphic.2

Litchfield School District Joins Mississippi Valley Property Casualty Cooperative for Insurance Coverage

Litchfield Community Unit School District #12 Board of Education Meeting | March 19, 2026 Article Summary: The Litchfield School Board unanimously approved a resolution to enter into an agreement with...