Litchfield Advances $23 Million Sewer Overhaul and Approves $112,000 in Emergency Water Plant Repairs

Litchfield City Council Meeting | April 2, 2026

Article Summary: The Litchfield City Council moved forward with massive infrastructure planning for its water and wastewater facilities while approving emergency expenditures to address catastrophic failures at the water treatment plant.

Litchfield Infrastructure Key Points:

  • Approved $112,699.03 in emergency repairs for the water plant, including a new PAC silo and security system, waiving competitive bidding.

  • CMT Engineering outlined a $22 to $23 million rehabilitation of the aging wastewater treatment plant, targeting state loans and principal forgiveness.

  • Water clarifiers have been cleaned and filters rebuilt, leading to immediate and noticeable water quality improvements.

  • New 8-inch water lines and a water tower cleaning are underway to address ongoing distribution and quality issues.

The Litchfield City Council on Thursday, April 2, 2026, tackled a series of critical infrastructure hurdles, unanimously approving emergency expenditures for the city’s water treatment plant while previewing a massive $23 million overhaul of the wastewater facility.

The emergency water plant repairs come after what the city’s administration described in agenda documents as a “catastrophic failure of its chemical feed system.” After site visits from both CMT Engineering and HMG Engineering, a voluminous list of immediate corrections was identified.

Alderman Bob Garcia motioned to waive customary bidding procedures to authorize $112,699.03 in emergency fixes. The expenditures include $83,343.00 for a Powered Activated Carbon (PAC) Silo, $4,446.20 for Chlorination and Ammonia Emergency Close Systems, and $24,909.83 for a comprehensive water plant security and access control system to be installed by Heart Technologies.

Christie from CMT Engineering provided an encouraging update on the water plant’s ongoing recovery. A Request for Proposals (RFP) for contract operations is currently out, with vendors touring the facility. Meanwhile, critical deferred maintenance is finally being addressed. Both clarifiers have been completely cleaned out, and the rehabilitation of three filters—comprised of sand and granular activated carbon—is underway.

The results are already visible. “The water after the clarifiers actually had a turbidity that was below the finished water level,” Christie told the council, noting the dramatic reduction of particles in the water. She added that the plant staff’s morale has skyrocketed as they receive proper training on troubleshooting and system functions. “The sense of pride in ownership that’s going on out there is just leaps and bounds from where it was.”

On the distribution side, the city is advancing a $1.5 million water project on the west side of the railroad tracks, funded by a grant, alongside a $2.2 million project to reroute an 8-inch water line on the east side of the lake. A comprehensive cleaning of the water tower is also imminent, which officials hope will further decrease resident complaints regarding water quality.

Simultaneously, the city is racing against the clock to secure funding for a massive overhaul of its wastewater treatment plant, which has reached the end of its extended life. The $22 to $23 million project will heavily focus on replacing deteriorating mechanical components while preserving the structurally sound concrete basins to save costs.

“At a wastewater plant, everything is concrete because the wastewater is corrosive. The structures have like a 50-to-100-year life expectancy. It’s the mechanical components that have that 20-year life expectancy,” Christie explained to the council. “The most economical infrastructure that you have is what you’ve already used and paid for.”

To fund the wastewater overhaul, Litchfield is preparing an application for the State Revolving Fund (SRF) loan program. The city is aggressively pushing to finalize designs and secure necessary construction permits to be placed on the state’s “intended use” list by July 1. Achieving this status is highly competitive but critical, as it opens the door to “principal forgiveness”—the EPA equivalent of grant money based on the city’s median household income.

“We don’t want to lose that principal forgiveness,” Christie emphasized, warning that missing the fiscal cycle could force the city to compete against a different pool of projects the following year with no guarantee of the same financial assistance.

The council will consider an engineering design contract at its next meeting to ensure the project meets the strict state deadlines.

Leave a Comment





Latest News Stories

Litchfield Park-Schalk Park Graphic Logo

Park Board Denies Request for Schalk Park Field Renovations

Litchfield Park District Board Meeting | Dec. 3, 2025 Article Summary: Citing concerns over historical preservation and limited future usability, the Park District Board rejected a request from LBI to...
Litchfield Park Logo Graphic.1

Litchfield Park Board Updates Master Plan, Approves Tax Ordinances

Litchfield Park District Board Meeting | Dec. 3, 2025 Article Summary: The Litchfield Park District Board updated its long-term strategy to maintain eligibility for state grants and passed three ordinances to...
Litchfield Logo Graphic.3

Litchfield Council Approves $230k in Emergency Water Plant Repairs Following System Failure

Litchfield City Council Meeting | Dec. 4, 2025 Article Summary: The Litchfield City Council authorized over $230,000 in emergency expenditures to repair the city’s water treatment plant following a "catastrophic...
montgomery county Graphic Logo.2

Roads & Bridges Committee: Wind Farm Proposed for Raymond-Nokomis Area; Engineer Salary Set

Montgomery County Roads & Bridges Committee | October 2025 Article Summary: Pattern Energy has initiated discussions with the county regarding a potential wind farm near Raymond and Nokomis. The Roads...
Montgomery County Bldg Grounds Committee

Buildings & Grounds Committee: Moves to Restore Courthouse Porch; EV Stations Proposed

Montgomery County Buildings & Grounds Committee | October 2025 Article Summary: The Buildings & Grounds Committee has advanced a proposal to restore the south porch of the Historic Courthouse. Hillsboro...
Meeting Briefs

Meeting Summary and Briefs: Litchfield City Council for Nov. 20, 2025

Litchfield City Council Meeting | Nov. 20, 2025 The Litchfield City Council met on Thursday, Nov. 20, 2025, for its final meeting before the Thanksgiving holiday. The session was dominated...
Montgomery County Personnel Committee

Development & Personnel Committee: County Awarded $1.1 Million DCEO Grant; Monitors State Control of Energy Zoning

Montgomery County Development & Personnel Committee | October 2025 Article Summary: Montgomery County has secured nearly $1.1 million in energy transition grants to support local projects. However, the committee is...
Meeting Briefs

Meeting Summary and Briefs: Litchfield CUSD 12 for November 18, 2025

Litchfield CUSD 12 Meeting | November 18, 2025 The Litchfield Community Unit School District No. 12 Board of Education met on Tuesday, November 18, 2025, to address a tentative tax...
Litchfield Logo.1

Council Approves Partnership with ‘Embrace the Lake’ Non-Profit

Litchfield City Council Meeting | Nov. 20, 2025 Article Summary: The City Council passed an ordinance authorizing the acceptance of funds from "Embrace the Lake Inc.," a newly formed 501(c)(3)...
montgomery county Graphic Logo.2

Coordinating Committee: Reviews Cemetery Laws and 2026 Schedule

Montgomery County Coordinating Committee | October 2025 Article Summary: The Coordinating Committee reviewed legal opinions regarding cemetery maintenance and moved forward with the appointment of a new State’s Attorney. The...
OLYMPUS DIGITAL CAMERA

Board Approves Future Administrator and Expels Student in Personnel Actions

Litchfield CUSD 12 Meeting | November 18, 2025 Article Summary: The Litchfield School Board approved several personnel changes, including the hiring of a new assistant principal and athletic director for...
Litchfield Logo Graphic.4

Litchfield Switches Insurance Carriers to IML-RMA, Anticipates Savings and Lower Deductibles

Litchfield City Council Meeting | Nov. 20, 2025 Article Summary: The Litchfield City Council approved a switch in the city's insurance provider to the Illinois Municipal League Risk Management Association...
Montgomery County Finance Committee

Finance Committee: Spreadsheet Error Forces $1 Million Budget Correction; Committee Balances FY26 Plan

Montgomery County Finance & Budget Committee | October 2025 Article Summary: A spreadsheet error omitting over $1 million in expenses has forced the Finance Committee to revise the 2026 budget....
Litchfield School Logo Graphic.5

Litchfield Schools Earn “Commendable” Ratings; High School Nears Top Tier

Litchfield CUSD 12 Meeting | November 18, 2025 Article Summary: A presentation on the annual State Report Card revealed that all schools in the Litchfield district achieved "Commendable" status. Litchfield...
Litchfield Logo Graphic.3

Litchfield Limits Winter Lake Draw Down to 3 Feet, Citing Erosion and Water Quality Concerns

Litchfield City Council Meeting | Nov. 20, 2025 Article Summary: The Litchfield City Council has decided to limit the annual winter draw down of Lake Lou Yaeger to three feet...