Litchfield Logo Graphic.3

Litchfield Advances $23 Million Sewer Overhaul and Approves $112,000 in Emergency Water Plant Repairs

Litchfield City Council Meeting | April 2, 2026

Article Summary: The Litchfield City Council moved forward with massive infrastructure planning for its water and wastewater facilities while approving emergency expenditures to address catastrophic failures at the water treatment plant.

Litchfield Infrastructure Key Points:

  • Approved $112,699.03 in emergency repairs for the water plant, including a new PAC silo and security system, waiving competitive bidding.

  • CMT Engineering outlined a $22 to $23 million rehabilitation of the aging wastewater treatment plant, targeting state loans and principal forgiveness.

  • Water clarifiers have been cleaned and filters rebuilt, leading to immediate and noticeable water quality improvements.

  • New 8-inch water lines and a water tower cleaning are underway to address ongoing distribution and quality issues.

The Litchfield City Council on Thursday, April 2, 2026, tackled a series of critical infrastructure hurdles, unanimously approving emergency expenditures for the city’s water treatment plant while previewing a massive $23 million overhaul of the wastewater facility.

The emergency water plant repairs come after what the city’s administration described in agenda documents as a “catastrophic failure of its chemical feed system.” After site visits from both CMT Engineering and HMG Engineering, a voluminous list of immediate corrections was identified.

Alderman Bob Garcia motioned to waive customary bidding procedures to authorize $112,699.03 in emergency fixes. The expenditures include $83,343.00 for a Powered Activated Carbon (PAC) Silo, $4,446.20 for Chlorination and Ammonia Emergency Close Systems, and $24,909.83 for a comprehensive water plant security and access control system to be installed by Heart Technologies.

Christie from CMT Engineering provided an encouraging update on the water plant’s ongoing recovery. A Request for Proposals (RFP) for contract operations is currently out, with vendors touring the facility. Meanwhile, critical deferred maintenance is finally being addressed. Both clarifiers have been completely cleaned out, and the rehabilitation of three filters—comprised of sand and granular activated carbon—is underway.

The results are already visible. “The water after the clarifiers actually had a turbidity that was below the finished water level,” Christie told the council, noting the dramatic reduction of particles in the water. She added that the plant staff’s morale has skyrocketed as they receive proper training on troubleshooting and system functions. “The sense of pride in ownership that’s going on out there is just leaps and bounds from where it was.”

On the distribution side, the city is advancing a $1.5 million water project on the west side of the railroad tracks, funded by a grant, alongside a $2.2 million project to reroute an 8-inch water line on the east side of the lake. A comprehensive cleaning of the water tower is also imminent, which officials hope will further decrease resident complaints regarding water quality.

Simultaneously, the city is racing against the clock to secure funding for a massive overhaul of its wastewater treatment plant, which has reached the end of its extended life. The $22 to $23 million project will heavily focus on replacing deteriorating mechanical components while preserving the structurally sound concrete basins to save costs.

“At a wastewater plant, everything is concrete because the wastewater is corrosive. The structures have like a 50-to-100-year life expectancy. It’s the mechanical components that have that 20-year life expectancy,” Christie explained to the council. “The most economical infrastructure that you have is what you’ve already used and paid for.”

To fund the wastewater overhaul, Litchfield is preparing an application for the State Revolving Fund (SRF) loan program. The city is aggressively pushing to finalize designs and secure necessary construction permits to be placed on the state’s “intended use” list by July 1. Achieving this status is highly competitive but critical, as it opens the door to “principal forgiveness”—the EPA equivalent of grant money based on the city’s median household income.

“We don’t want to lose that principal forgiveness,” Christie emphasized, warning that missing the fiscal cycle could force the city to compete against a different pool of projects the following year with no guarantee of the same financial assistance.

The council will consider an engineering design contract at its next meeting to ensure the project meets the strict state deadlines.

Leave a Comment





Latest News Stories

Montgomery County Highway Committee

“Irresponsible Contractor”: Highway Committee Moves to Ban Firm After Bridge Project Issues

Montgomery County Roads & Bridges Committee | November Meeting Article Summary: The Montgomery County Roads & Bridges Committee is moving to blacklist a contractor after the County Engineer reported serious...
Litchfield Logo Graphic.4

Engineer Updates Litchfield Council on Water Plant Issues, Maintenance Needs

Litchfield City Council Meeting | December 18, 2025 Article Summary: An engineer from Crawford, Murphy & Tilly addressed the Litchfield City Council regarding recent water turbidity violations and taste issues,...
Litchfield School Logo Graphic.5

Litchfield Board Approves 2025 Tax Levy Following Public Hearing

Litchfield Community Unit School District No. 12 Meeting | December 16, 2025 Article Summary: The Litchfield Community Unit School District No. 12 Board of Education approved the 2025 tax levy...
Meeting Briefs

Meeting Summary and Briefs: Montgomery County Board for Nov. 12, 2025

Montgomery County Board Meeting | Nov. 12, 2025 Overall Meeting SummaryThe Montgomery County Board met on Tuesday, November 12, 2025, for a session dominated by the passage of the Fiscal...
montgomery county Graphic Logo.3

Board Approves Courthouse Porch Repairs; Updates on Maintenance Projects

Montgomery County Board Meeting | Nov. 12, 2025 Article Summary: The Montgomery County Board authorized nearly $18,000 in repairs for the Historic Courthouse porch and addressed maintenance issues caused by...
montgomery county Graphic Logo

Shaw Appointed State’s Attorney; Mullen Named Supervisor of Assessments

Montgomery County Board Meeting | Nov. 12, 2025 Article Summary: The Montgomery County Board filled two high-profile vacancies on Tuesday, appointing a new State’s Attorney and a Supervisor of Assessments...
Meeting Briefs

Meeting Summary and Briefs: Litchfield Park District Board for Dec. 3, 2025

Litchfield Park District Board Meeting | Dec. 3, 2025 The Litchfield Park District Board met on Tuesday, December 3, 2025, to address end-of-year business, including the approval of the annual...
Meeting Briefs

Meeting Summary and Briefs: Litchfield City Council for Dec. 4, 2025

Litchfield City Council Meeting | Dec. 4, 2025 The Litchfield City Council handled significant infrastructure and planning business during its Dec. 4, 2025, meeting. The board focused heavily on water...
montgomery county Graphic Logo.2

County Awards $1M in Energy Grants; Discusses New Wind Farm and EV Chargers

Montgomery County Board Meeting | Nov. 12, 2025 Article Summary: Montgomery County continues to expand its energy portfolio, accepting over $1 million in state transition grants while opening discussions for...
Litchfield Logo Graphic.4

Litchfield Approves $1.7M Water Main Project, Authorizes Change Order for State Street

Litchfield City Council Meeting | Dec. 4, 2025 Article Summary: The City Council moved forward with significant infrastructure improvements, accepting a $1.7 million bid for water main replacements and approving...
Litchfield Park-Walton Park Graphic Logo

Mayor Fleming Questions Winter Closure of Walton Park

Litchfield Park District Board Meeting | Dec. 3, 2025 Article Summary: Litchfield Mayor Jacob Fleming attended the Park Board meeting to inquire why Walton Park is closed to the public...
montgomery county Graphic Logo.4

Consultant Error Forces Scramble; County Board Approves FY2026 Budget with Surplus

Montgomery County Board Meeting | Nov. 12, 2025 Article Summary: After discovering a significant vendor error that under-reported expenses by over $1 million during the drafting process, the Montgomery County...
Litchfield Logo Graphic.3

Marshalls or T.J. Maxx? Litchfield Amends Agreement to Court Retailer

Litchfield City Council Meeting | Dec. 4, 2025 Article Summary: The City Council approved an amendment to a development agreement for 1403 W. Ferdon St., allowing the developer to secure...
Litchfield Park-Pool Graphic Logo

Park District Plans Pool Repairs, Approves Staff Training

Litchfield Park District Board Meeting | Dec. 3, 2025 Article Summary: The Litchfield Park District Board authorized funding for specialized staff training and outlined necessary equipment repairs ahead of the 2026...
Litchfield Logo Graphic.4

Council Adopts Updated Parks Master Plan, Scrubs Reference to Corvette Drive Sports Complex

Litchfield City Council Meeting | Dec. 4, 2025 Article Summary: The City Council adopted an updated Parks and Recreation Master Plan required for state grant funding but first amended the...