Board Approves $440,000 Architect Fee Increase for Campus Master Plan
LLCC Board of Trustees Meeting | December 15, 2025
Article Summary: The LLCC Board of Trustees approved a modification to the agreement with Demonica Kemper Architects, increasing fees by $440,000. The additional funds cover expanded design scopes for renovations to Sangamon Hall and Menard Hall as part of the college’s Master Plan Implementation.
Master Plan Key Points:
-
Fee Increase: The contract with Demonica Kemper Architects was modified to include an additional $440,000 for architectural, engineering, and abatement services.
-
Expanded Scope: The modification addresses additional renovations required for The Learning Center (library) on the first floor of Sangamon Hall and mechanical controls upgrades.
-
Timeline: Bidding for Phase A3 (Sangamon Hall) is expected in early 2026, with construction on various phases extending through 2028.
SPRINGFIELD — The scope of renovations at Lincoln Land Community College’s main campus is expanding, prompting the Board of Trustees to approve a $440,000 increase in architectural fees on Monday, December 15, 2025.
The board voted to modify the existing agreement with Demonica Kemper Architects (DKA). The additional funds will cover unforeseen design and engineering work for the Master Plan Implementation Phase A3, specifically regarding renovations to Sangamon Hall.
According to board documents, the original scope for the first floor of the library, now named The Learning Center (TLC), required adjustments. Recent realignments of services necessitated changes to the layout, additional service desks, and student study areas.
The fee increase also covers design work for protection, health, and safety projects and mechanical controls upgrades in Sangamon Hall.
The construction timeline provided to the board indicates a multi-year process. Bidding for Phase A3 is set for early 2026. Subsequent phases involving Menard Hall (Phases B and C) are scheduled for bidding in late 2026 and construction through 2028.
Event Calendar
Latest News Stories
Consultant Error Forces Scramble; County Board Approves FY2026 Budget with Surplus
Marshalls or T.J. Maxx? Litchfield Amends Agreement to Court Retailer
Park District Plans Pool Repairs, Approves Staff Training
Council Adopts Updated Parks Master Plan, Scrubs Reference to Corvette Drive Sports Complex
Park Board Denies Request for Schalk Park Field Renovations
Litchfield Park Board Updates Master Plan, Approves Tax Ordinances
Litchfield Council Approves $230k in Emergency Water Plant Repairs Following System Failure
Roads & Bridges Committee: Wind Farm Proposed for Raymond-Nokomis Area; Engineer Salary Set
Buildings & Grounds Committee: Moves to Restore Courthouse Porch; EV Stations Proposed
Meeting Summary and Briefs: Litchfield City Council for Nov. 20, 2025
Development & Personnel Committee: County Awarded $1.1 Million DCEO Grant; Monitors State Control of Energy Zoning
Meeting Summary and Briefs: Litchfield CUSD 12 for November 18, 2025