Litchfield Upgrades Water Main Project on State Street Following Resident Concerns
Litchfield City Council Meeting | Sept. 18, 2025
Article Summary: The City Council approved a nearly $100,000 change order to upgrade a water main project on State Street from 8-inch to 12-inch pipes. The decision came after input from a local fire safety expert regarding water flow and future firefighting capabilities.
Water Main Upgrade Key Points:
-
Change Order: The council approved a $97,193 change order for Petersburg Plumbing Inc.
-
Pipe Size: The project will now install a 12-inch water main instead of the originally planned 8-inch main along State Street.
-
Increased Flow: The upgrade significantly increases water flow from approximately 1,500 gallons per minute to 3,500 gallons per minute.
-
Fire Safety: The change was prompted by a request from a citizen with expertise in fire safety, aiming to maximize water supply for future development and emergencies.
A water infrastructure project on State Street is getting a significant upgrade after the Litchfield City Council voted to increase the pipe size on Wednesday, Sept. 18, 2025.
The council unanimously approved a change order of $97,193 to Petersburg Plumbing Inc. to install a 12-inch water main instead of the planned 8-inch line. The project covers State Street from Edwards Street to Weir Street.
City Administrator Adam Pennock explained that a citizen reached out to several aldermen requesting the change. Alderperson Josh Hughes identified the citizen as an employee of Mac’s Fire & Safety, who argued that maximizing the water supply now would be more cost-effective than needing to upgrade again in the future.
“The work was done by the engineer to determine the difference,” Pennock said. “With the 8-inch line, [we would] be able to service about 1,500 gallons per minute… with the 12-inch line, you’d be able to pull about 3,500 gallons per minute.”
Pennock noted that while the 8-inch line would have been sufficient for current needs, the 12-inch line offers better long-term capacity. The additional cost will be covered by funds from the TIF 1 fund.
Event Calendar
Latest News Stories
County Engineer Raises Concerns Over “Irresponsible” Bridge Contractor
Board Approves New Labor Contracts for Circuit Clerk, Assessment Employees
Litchfield Park District Weighs Contracting Concrete Work for Facility Upgrades
Meeting Summary and Briefs: City of Litchfield for January 6, 2026
Retirements and resignations to impact midterms as balance of power at stake
U.S. Supreme Court to hear anti-oil cases with energy costs on the line
Constitutional concerns raised over Illinois’ first civil hate crime case
Residents Voice Frustrations Over Oil and Chip Street Conditions
Newsom predicts smaller budget shortfall than state agency
Colorado ordered to pay $5.4M after abortion law blocked
Four Republicans certified for primary to take on Pritzker
Illinois quick hits: State sues over frozen funds; Nicor Gas seeks rate hike