Litchfield Upgrades Water Main Project on State Street Following Resident Concerns
Litchfield City Council Meeting | Sept. 18, 2025
Article Summary: The City Council approved a nearly $100,000 change order to upgrade a water main project on State Street from 8-inch to 12-inch pipes. The decision came after input from a local fire safety expert regarding water flow and future firefighting capabilities.
Water Main Upgrade Key Points:
-
Change Order: The council approved a $97,193 change order for Petersburg Plumbing Inc.
-
Pipe Size: The project will now install a 12-inch water main instead of the originally planned 8-inch main along State Street.
-
Increased Flow: The upgrade significantly increases water flow from approximately 1,500 gallons per minute to 3,500 gallons per minute.
-
Fire Safety: The change was prompted by a request from a citizen with expertise in fire safety, aiming to maximize water supply for future development and emergencies.
A water infrastructure project on State Street is getting a significant upgrade after the Litchfield City Council voted to increase the pipe size on Wednesday, Sept. 18, 2025.
The council unanimously approved a change order of $97,193 to Petersburg Plumbing Inc. to install a 12-inch water main instead of the planned 8-inch line. The project covers State Street from Edwards Street to Weir Street.
City Administrator Adam Pennock explained that a citizen reached out to several aldermen requesting the change. Alderperson Josh Hughes identified the citizen as an employee of Mac’s Fire & Safety, who argued that maximizing the water supply now would be more cost-effective than needing to upgrade again in the future.
“The work was done by the engineer to determine the difference,” Pennock said. “With the 8-inch line, [we would] be able to service about 1,500 gallons per minute… with the 12-inch line, you’d be able to pull about 3,500 gallons per minute.”
Pennock noted that while the 8-inch line would have been sufficient for current needs, the 12-inch line offers better long-term capacity. The additional cost will be covered by funds from the TIF 1 fund.
Event Calendar
Latest News Stories
Litchfield Approves $397k for Emergency Water Plant Repairs; Resident Donates $100k to Cause
Litchfield Park Board Approves 5% Tax Levy Increase
Meeting Summary and Briefs: Litchfield CUSD 12 for October 21, 2025
Principals Present Improvement Plans Focused on Growth and Attendance
Litchfield Board Approves Strategic Planning Contract and Truck Driver Training Site
Litchfield School Board Accepts Clean Financial Audit; Auditors Advise Monitoring Benefit Funds
Meeting Summary and Briefs: Litchfield City Council for Oct. 16, 2025
Litchfield Approves Contract for State-Funded Auto Theft Task Force Inspector
Council Rejects Water Bill Credit for Mt. Olive, Citing Fairness to Local Residents
Litchfield Council Authorizes $183K in Emergency Water Plant Repairs Following System Failure
Meeting Summary and Briefs: Litchfield City Council for Oct. 2, 2025
Litchfield Approves New Police Vehicle Upfit and Pursuit of Full-Time Chief